Estimate At Completion (EAC) – A Project Forecasting Tool

The Estimate At Completion (EAC) is the forecasted value of the project when it completes. It is only an indicator of how much the project may cost you to complete it.

As you know that the projects are executed in the real world, and in the real world things do not always go in a textbook way. There will be many situations beyond your control that may make your project deviate from the approved baselines. Consequently, your project schedule and budget may change.

The PMBOK Guide defines two project forecasting tools:

Estimate To Complete (ETC) is the amount of money used to complete the remaining work (the work that is left after certain period).

Estimate At Completion (EAC) is the amount of money that the project will cost you in the end.

These forecasting tools provide you the visibility of future progress of the project and give project sponsors an early idea of how much they are going to spend on it.

A prudent project manager always keeps track of changes and informs the management.

There are various circumstances and formulas in which EAC can be calculated, but from a PMP Certification point of view, is one formulathat is most commonly used, and more popular than the rest.

That is,

Estimate At Completion = (Budget at Completion) / (Cost Performance Index)

EAC = BAC/CPI

This formula provides the EAC if the CPI remains present throughout the project. It should be noted that if the CPI = 1, then EAC = BAC. Also, when the project starts, EAC equals to BAC.

I am going to give you an example based on this formula only. Once you understand the concept, you can go through your reference books and the PMBOK Guide to analyze the remaining formulas.

However, for the PMP Certification exam this formula is enough and there is less chance that you will see questions based on other typical formulas.

Therefore, if you understand and are able to solve questions based on this formula then you wouldn’t have any problem in your exam.

Example:

You have a project to be completed in 12 months and the total cost of the project is $100,000. Six months have passed and $60,000 is spent but on closer review you find that only 40% of the work is completed so far.
Find the Estimate At Completion (EAC) for this project.

Given in question:

Budget At Completion = $100,000

Actual Cost (AC) = $60,000

Planned Value (PV) = 50% of $100,000

= $50,000

Earned Value (EV) = 40% of $100,000

= $40,000

Cost Performance Index (CPI) = EV / AC

= $40,000 / $60,000

= 0.67

Hence,

Cost Performance Index (CPI) = 0.67

Now,

Estimate At Completion (EAC) = BAC/CPI

= $100,000/0.67

= $149,253.73

Hence,

Estimate At Completion (EAC) = $149,253.73

It means that, if the project continues to progress with CPI = 0.67 til the end, then you will have to spend $149,253.73 to complete the project.

In the next blog we will discuss the Estimate To Complete (ETC).

 

image credit => nuchylee / FreeDigitalPhotos.net

8 Responses to “Estimate At Completion (EAC) – A Project Forecasting Tool”

Read below or add a comment...

  1. Hannah says:

    PMBok Guide has 2 other formulas for EAC:

    EAC=AC+BAC-EV
    EAC=AC+(BAC-EV)/(CPI x SPI)

    Could you please explain these 2 formulas?

    • Fahad Usmani says:

      Hello Hannah,

      Sorry to replying you late as I was busy with celebrating Eid Holidays with my family.

      Anyway, the PMBOK mentions three formulas to calculate the EAC under three different circumstances, those are as follows:

      1. EAC = BAC/CPI => In this scenario you will simply assume that you will continue to perform the work till the end as you were doing till now. In other words, your future performance will be same as the current and past performance.
      2. EAC = AC + BAC – EV => Here, you will simply say that till now you are deviated from your forecasted budget estimate; however, from now onwards you can complete the remaining work as you have calculated. That is why in this formula, to calculate the EAC you will simply add money spend till now (i.e. AC) and budgeted cost to be spend for remaining work.
      3. EAC = AC + (BAC – EV)/(CPI*SPI) => In this case not only the cost but schedule also has to be taken into the consideration. In other words you can say that, your cost performance is negative and you are behind the schedule and you must complete your project within the date agreed on the schedule.

      Hope this answers your query.

  2. Kupa says:

    Loving the Study Notes section…Great job!

  3. Paul Evans says:

    Found your site today in my PMP study time and wanted to say I really like your logical and simplifed approach.
    Regards…Paul.

  4. Paul Evans says:

    Sorry I also wanted to say that I’m looking forward to your next blog on ETC…Cheers…Paul.

Got something to say?

*