What is a Stakeholder in Project Management?

Fahad Usmani, PMP

A stakeholder in project management is a person, group, or organization affected by the project or its outcome or has any interest in the project. 

According to the PMBOK Guide, “A stakeholder is an individual, group, or organization who may affect, be affected by or perceive itself to be affected by a decision, activity, or outcome of a project.”

Small projects have a few stakeholders; however, larger projects have many stakeholders, including communities and the public. In these cases, managing stakeholders can be challenging.

For example, a dam construction project has many stakeholders, such as the government, local authorities, the population that will be displaced, the population continuing to reside near the dam, environmentalists, the project management team, higher management, etc.

Not all stakeholders are equal. Some are powerful, others not noninfluential, and they will have different requirements and expectations. You should treat them according to their influence on the project or its objective, requirements, and expectations. Failing to do so can jeopardize your project’s success.

In this case, you can prioritize and group the stakeholders into key and non-key stakeholders.

Stakeholders Vs Key Stakeholders

As I explained earlier, a stakeholder is someone who is impacted by or has an interest in your project. They can be internal (project team, management) or external (customers, suppliers, regulators).

While a project can have many stakeholders, key stakeholders are the most influential and critical to its success. They have significant power, interest, or control over the project’s resources or outcomes. These include sponsors, high-level decision-makers, or any party heavily impacted by the project’s results.

While all stakeholders deserve attention, key stakeholders require focused engagement because they can influence decisions, provide resources, or create roadblocks. Prioritizing key stakeholders helps ensure project alignment with critical goals, reduces risks, and promotes smoother communication throughout the project lifecycle. 

You must identify key stakeholders early to complete the project with minimal obstruction.

Overlooking any important stakeholder can make the situation difficult later. It may cause a project delay, cost overrun, and, in the most severe cases, abrupt project termination.

Examples of Project Stakeholders

Below are lists of stakeholders divided into key and non-key stakeholders:

Key Stakeholders

  • Project Sponsor
  • Project Manager
  • Senior Leadership/Executive Team
  • Clients/Customers 
  • Functional Managers
  • Vendors/Suppliers
  • Regulators
  • Project Team Members

Non-Key Stakeholders

  • Support Staff 
  • General Employees
  • Local Community
  • Media
  • Industry Associations

Types of Stakeholders in Project Management

chart showing example of stakeholder internal

Project stakeholders can be grouped into two categories:

  1. Internal Stakeholders
  2. External Stakeholders

Internal Stakeholders

Internal stakeholders are within the organization. They are directly involved with the project or work with the organization managing it.

Example of Internal Stakeholders

  • A sponsor
  • An internal customer or client (if the project is for an internal need of an organization)
  • A project team
  • A program manager
  • A portfolio manager
  • Management
  • Another group’s manager (e.g., functional manager, operational manager, admin manager, etc.).

These stakeholders generally have the highest interest in the project’s success.

External Stakeholders

External stakeholders are outside the organization. They are not directly involved with the project but indirectly affected by the project or its outcome.

Example of External Stakeholders

  • An external customer or client (if the project is a result of a contract)
  • An end user of the project’s outcome
  • A supplier
  • Subcontractors
  • The government
  • Local authorities
  • Local communities
  • The media

As you can see, external stakeholders include clients, governments, and local authorities, which are powerful entities. Therefore, you must manage them carefully.

Identifying Project Stakeholders

To identify project stakeholders, start by reviewing your project’s objectives. Think about everyone who might be affected by the project or is interested in its success. Stakeholders can be people or groups inside or outside your organization.

First, look at internal stakeholders. These include the project team, project manager, and sponsors. Also, consider departments like finance, marketing, or IT that might contribute to or be impacted by the project.

Next, consider external stakeholders. These can be customers who will use the project’s outcome, suppliers providing materials, or regulatory bodies that need to approve the project. Don’t forget local communities, especially if the project affects the public.

Talk to experts, team members, and leaders who know the project well. Conduct brainstorming sessions.

Organize your list by writing down each stakeholder’s role and how the project affects them. To spot key stakeholders, focus on those with the most influence or interest. Always update your list as the project progresses.

How to Manage Project Stakeholders

To manage your project stakeholders, follow the steps below.

1. Identify Stakeholders

After signing the project charter, you should identify your project stakeholders. You can start reviewing project documents such as the project charter, procurement documents, agreements, and previous checklists. Some useful tools and habits include brainstorming, facilitated workshops, interviews, etc.

2. Stakeholder Analysis

After identifying stakeholders, you should analyze them to find their interests and influence on the project. You can use the salience model, power/interest grid, or another suitable method for stakeholder analysis.

3. Prioritize Stakeholders

After analyzing project stakeholders, you must prioritize them according to their power and interest in the project. Prioritization will provide information on stakeholders who require more attention or can be ignored. 

4. Develop a Stakeholder Management Plan

Based on the information collected, you will develop your stakeholder engagement plan, which will provide information on handling each stakeholder. An influential and powerful stakeholder will receive more attention than a low-power and low-interest group of stakeholders.

Positive Stakeholders and Negative Stakeholders

Stakeholders can be positive or negative.

A positive stakeholder sees the project’s positive side and benefits from its success. These stakeholders help the project management team to complete the project successfully.

On the other hand, a negative stakeholder sees the outcome and may be negatively impacted by the project or its outcome. This type of stakeholder is less likely to contribute to the project’s success.

Many professionals think competitors are negative stakeholders, as your project also affects them. However, competitors are not negative stakeholders because you manage your stakeholders proactively and fulfill their requirements, but you cannot manage or fulfill your competitors’ requirements.

You should identify your stakeholders early in the project and record them in the stakeholder register.

Stakeholder Vs Shareholder

Stakeholder and shareholder are different terms, though many professionals confuse these terms with each other.

A stakeholder is a person or group with any interest in the project or is impacted by its outcome. On the other hand, a shareholder has a financial investment in the project or the business. All shareholders are stakeholders, but not all stakeholders are shareholders.

Summary

Stakeholders are individuals or groups affected by or interested in the project. It is important to identify stakeholders at the beginning of the project and develop a strategy to manage them and their requirements. This will help you complete the project with minimal obstruction because obtaining their positive involvement with your project will provide the support you need.

Further Readings:

This topic is important from a PMP certification exam point of view.

Fahad Usmani, PMP

I am Mohammad Fahad Usmani, B.E. PMP, PMI-RMP. I have been blogging on project management topics since 2011. To date, thousands of professionals have passed the PMP exam using my resources.

PMP Question Bank

This is the most popular Question Bank for the PMP Exam. To date, it has helped over 10,000 PMP aspirants prepare for the exam. 

PMP Training Program

This is a PMI-approved 35 contact hours training program and it is based on the latest exam content outline applicable in 2026.

Similar Posts

61 Comments

  1. can you explain types of stakeholders in terms of 1) neutral stakeholders 2) Supportive stakeholders 3) leading stakeholders 4) Influencing stakeholders

  2. Really great article that’s helped me a lot today with my studies. Thank you. Researching shareholders next!

    1. A deliverable is a tangible or intangible good or service produced as a result of a project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report, a document, a software product, a server upgrade or any other building block of an overall project. (Source: Wikipedia)

  3. I am preparing for the CAPM exam, I was wondering if you could guide or give out some tips that would benefit me in preparing for the exam. Your guidance will be greatly appreciated.
    Thank you.

  4. Thanks fahad for this article, pls can u direct me to a Web site where i can get ” The role of user as stakeholder in project management process”.

  5. This is superb contributions to PM student, but what of categories of stake holders, as antogonistic, low priority as well as supportive stake holders taught by my lecturer???

    1. You can define how are you going to classify stakeholder in your project management plan and go for it.

  6. Hello, I am a student and this is really beneficial for me.
    Just wanted to know if you could give me the questionnaire of this research it would be really helpful.

  7. Dear Mr. Fahad

    If i still have some invoices not paid to the seller , is this mean the project still not closed ???

    Thanks

      1. One of the best explanations and easy to understand, Thankyou for posted that data for guiding us!
        keep posting all relevent material of Project managemnet.

    1. You need to separate true stakeholders from project team members and SMEs. The true stakeholders are identified through understanding the organisation, operating model and also related dependent projects.