Managing project costs can feel tricky, especially when performance starts to slip. That’s where the TCPI calculator becomes useful. The To-Complete Performance Index (TCPI) shows the cost efficiency your team must achieve on the remaining work to meet a target budget. This target can be the original budget or a revised estimate. Instead of guessing, you get a clear number that tells you how hard your team needs to work moving forward.
In this blog post, you will learn how TCPI works, how to calculate it, and how a TCPI calculator helps you make better cost decisions quickly.
TCPI Calculator
Use the calculators below to find TCPI for your project. The first calculator uses BAC. The second calculator uses EAC. TCPI has two formulas, depending on whether you are trying to finish within the original budget or within a revised estimate.
TCPI Calculator Using BAC
Use the TCPI calculator below to calculate TCPI using BAC:
TCPI Calculator Using BAC
Formula: TCPI = (BAC – EV) / (BAC – AC)
TCPI Calculator Using EAC
Use the TCPI calculator below to calculate TCPI using EAC:
TCPI Calculator Using EAC
Formula: TCPI = (BAC – EV) / (EAC – AC)
How to Calculate TCPI
You can calculate TCPI in a few simple steps. First, collect the main earned value numbers. These include BAC, EV, AC, and sometimes EAC. Then choose the right formula based on your cost situation. When you are working toward the original budget, you use the BAC-based formula. When you are over budget and working with a revised forecast, you use the EAC-based formula.
Step 1: Find Budget at Completion (BAC)
BAC is the total approved budget for the project. It shows how much money the project was supposed to cost when it was first planned.
Step 2: Find Earned Value (EV)
EV is the value of the work completed so far. It shows how much of the planned budget you have earned from completed work.
Step 3: Find Actual Cost (AC)
AC is the amount of money already spent on the project. You compare it with EV to understand cost performance.
Step 4: Choose the Right TCPI Formula
Use this formula when you want to complete the project within the original budget:
TCPI = (BAC – EV) ÷ (BAC – AC)
Use this formula when you expect to complete the project using a revised estimate:
TCPI = (BAC – EV) ÷ (EAC – AC)
Step 5: Interpret the Result
A TCPI of 1 means you need exact budget efficiency on the remaining work. A value below 1 means the remaining work is easier to fund. A value above 1 means you need stronger cost control from this point forward.
To-Complete Performance Index Formula
The TCPI formula depends on the cost target you want to meet. You have two formulas:

Here:
BAC = Budget at Completion
EV = Earned Value
AC = Actual Cost
EAC = Estimate at Completion
TCPI = To-Complete Performance Index
TCPI Example Using BAC
Imagine your project has a BAC of $200,000. The EV is $120,000, and the AC is $110,000. Now apply the formula:
TCPI = (BAC – EV) ÷ (BAC – AC)
TCPI = (200,000 – 120,000) ÷ (200,000 – 110,000)
TCPI = 80,000 ÷ 90,000
TCPI = 0.89
This means the project needs a future cost efficiency of 0.89 to finish within the original budget.
TCPI Example Using EAC
Now imagine a project with BAC = $100,000, EV = $40,000, AC = $60,000, and a revised EAC = $149,253.73. Use the EAC-based formula:
TCPI = (BAC – EV) ÷ (EAC – AC)
TCPI = (100,000 – 40,000) ÷ (149,253.73 – 60,000)
TCPI = 60,000 ÷ 89,253.73
TCPI = 0.67
This means the project can continue with similar cost efficiency and still meet the revised estimate.
Importance of TCPI
TCPI helps project managers see how hard the team must work, from a cost perspective, to meet the budget goal. It supports better forecasting, early corrective action, and clearer communication with sponsors and clients. It also works well with CPI, SPI, and other earned value metrics because it adds a forward-looking view. Why guess about future performance when one number can show the pressure ahead?
FAQ
Q1. What is the To-Complete Performance Index?
TCPI is a project management metric that indicates the cost efficiency required to complete the remaining work and meet a budget target.
Q2. How do you calculate TCPI?
You calculate TCPI with one of two formulas: (BAC – EV) ÷ (BAC – AC) or (BAC – EV) ÷ (EAC – AC), depending on the target cost.
Q3. What does a TCPI greater than 1 mean?
A TCPI greater than 1 means the project must perform more efficiently in the future to meet the cost target.
Q4. When should I use the BAC-based formula?
Use the BAC-based formula when you want to finish the project within the original approved budget.
Q5. When should I use the EAC-based formula?
Use the EAC-based formula when the project is over budget, and you are working with a revised estimate at completion.
Summary
The To-Complete Performance Index is a useful metric for forecasting project cost performance. It shows the efficiency needed on the remaining work to meet either the original budget or a revised estimate. A TCPI calculator saves time, reduces manual error, and helps you make better cost decisions. When you use TCPI with other earned value metrics, you get a clearer view of where the project stands and what it will take to finish successfully.

I am Mohammad Fahad Usmani, B.E. PMP, PMI-RMP. I have been blogging on project management topics since 2011. To date, thousands of professionals have passed the PMP exam using my resources.
