Finish-to-Start Relationship in Project Management

Fahad Usmani, PMP

Today, we will discuss the finish-to-start relationship. This is the most commonly used relation in the network diagram.

Before we discuss the finish-to-start (FS) relationship in detail, let’s understand the terms we’ll use.

A predecessor activity comes before a dependent activity in a schedule. A successor activity is a dependent activity that comes after another.

A lead is when a successor activity is started before the predecessor finishes and is indicated by the “-” sign.

A lag is a delay of a successor activity, denoted by the “+” sign. 

Finish-to-Start Relationship

A project network diagram can have four types of dependency:

  1. Finish-to-start
  2. Finish-to-finish
  3. Start-to-finish
  4. Start-to-start

In this blog post, I will provide details of the finish-to-start (FS) relationship.

The PMBOK Guide states, “Finish to Start is a Logical Relationship in which a Successor Activity cannot start until a Predecessor Activity has finished.”

This is the most commonly used relationship in a network diagram; the start of the successor activity depends on the predecessor activity’s finish.

Representation of Finish-to-Start Activity

Here is how a finish-to-start relationship is shown in a network diagram.

finish to start

The bar chart or Gantt chart of the same is below:

finish to start relationship on a gantt chart

Example of Finish-to-Start Relationship

Let’s say you are constructing a room.

To install the ceiling, you have to construct the walls. In this example, the first activity is constructing walls, and the second activity is the ceiling.

Let’s see a scenario with lag.

After plastering the wall, you will wait two days for it to cure before starting to paint. Here, the relation is finish-to-start with two days of lag.

The next example has lead.

Suppose you are constructing a two-floor building. You have two activities in sequence: electrical work and painting. The electrical work will take ten days, and the painting will take six days.

However, as you complete the electrical work on the ground floor in five days, you begin painting while the electrical work on the second floor continues.

Here, you have a finish-to-start relationship with five days of lead.

Uses of Finish-to-Start Relationship

This relationship is used in all types of project network diagrams, including activity-on-node diagrams and activity-on-arrow diagrams.

Roles of Finish-to-Start Relation in Schedule Compression

This relationship is useful when the project is delayed, and the project manager has to compress the schedule.

Finish-to-start is also useful when you want to complete the project earlier and are looking for activities that can be run in parallel. 

Conclusion

Finish-to-start is the most commonly used relationship in project scheduling. This relationship is crucial for developing project timelines and ensuring that tasks are executed in the correct order. By understanding this relationship, project managers can create more efficient schedules, improve resource allocation, and complete the project with minimal obstruction.

Here is where this post on the finish-to-start relationship ends.

Further Readings:

This topic is important from a PMP exam point of view.

Fahad Usmani, PMP

I am Mohammad Fahad Usmani, B.E. PMP, PMI-RMP. I have been blogging on project management topics since 2011. To date, thousands of professionals have passed the PMP exam using my resources.

PMP Question Bank

This is the most popular Question Bank for the PMP Exam. To date, it has helped over 10,000 PMP aspirants prepare for the exam. 

PMP Training Program

This is a PMI-approved 35 contact hours training program and it is based on the latest exam content outline applicable in 2026.

Similar Posts

Leave a Reply

Your email address will not be published. Required fields are marked *