Planned Value (PV), Earned Value (EV) & Actual Cost (AC) in Project Cost Management

Fahad Usmani, PMP

Controlling costs and managing the schedule are key to project success. According to a 2025 PMI report, 9 out of 10 projects experience cost overruns, often exceeding budgets by up to 100%. Earned value management (EVM) provides a proven framework for tracking progress, identifying issues early, and staying on budget and schedule. 

In today’s blog post, I will dive deep into its core elements: Planned Value (PV), Actual Cost (AC), and Earned Value (EV). Whether you’re prepping for the PMP exam or leading real-world projects, you’ll learn how these metrics work, with updated formulas, examples, and the latest trends, such as predictive analytics.

If math feels tricky, don’t worry—we’ll go through it step by step. Keep your PMP reference book close for practice. By the end, you’ll know how to calculate Planned Value, Earned Value, and Actual Cost, figure out variances easily, and use EVM to spot and fix project issues early.

But first, let us understand earned value management.

NB: Although I will explain each element thoroughly, I suggest you keep a good PMP exam reference book for further reading and practice questions.

What is Earned Value Management?

Earned value management integrates scope, schedule, and cost to give you a clear performance snapshot.

image showing core elements (pv, ev & ac) of earned value management

The three pillars—PV, EV, and AC—form the basis for metrics like cost variance (CV) and schedule performance index (SPI). Why does this matter? A McKinsey analysis of over 300 megaprojects revealed average cost overruns of 80%, because issues weren’t identified early. Earned Value Management helps you catch these problems before they become major issues.

Planned Value (PV): Your Project Baseline

Planned Value represents the authorized budget for work scheduled up to a specific point. In simple terms, it’s what you should have earned if everything stayed on track. Per PMBOK Guide 7th Edition, “PV is the authorized budget assigned to scheduled work.”

Think of PV as your roadmap’s cost projection. The total PV at project end equals the budget at completion (BAC). It’s also called Budgeted Cost of Work Scheduled (BCWS), though PMBOK prioritizes the modern term.

Formula for Planned Value (PV)

The formula to calculate Planned Value is simple. Multiply the planned percentage of completed work by the project budget to get the Planned Value.

PV = (Planned % Complete) × BAC

Example of Planned Value (PV)

You have a project to be completed in 12 months. The budget of the project is 100,000 USD. Six months have passed, and the schedule says that 50% of the work should be completed. What is the project’s Planned Value (PV)?

Given in this question.

Project duration: 12 months

Project cost (BAC): 100,000 USD

Time elapsed: 6 months

Percent complete: 50% (as per the schedule)

Planned Value is the Value of the work that should have been completed so far (as per the schedule).

In this case, we should have completed 50% of the total work.

Planned Value = 50% of the Value of the total work

= 50% of BAC

= 50% of 100,000

= (50/100) X 100,000

= 50,000 USD

Therefore, the project’s Planned Value (PV) is 50,000 USD.

Applications of Planned Value (PV)

PV shines in early warnings. Use it to:

  • Calculate schedule variance (SV = EV – PV).
  • Forecast completion with schedule performance index (SPI = EV / PV).
  • Integrate with agile sprints for hybrid tracking.

Question for you: How often do you review your baseline? Regular checks prevent scope creep.

Actual Cost (AC): Tracking Real Expenses

Actual Cost is the money spent so far on completed work—no more, no less. It’s your project’s real-world bill, capturing labor, materials, and overhead.

The PMBOK Guide 7th edition defines it as “The realized cost incurred for the work performed on an activity during a specific time period.”

Actual Cost is also known as Actual Cost of Work Performed (ACWP).

Formula for Actual Cost (AC)

Finding Actual Cost is the simplest of all.

No formula needed—it’s straight from your ledger. Sum invoices, payroll, and vendor payments to date.

Example of Actual Cost (AC)

You have a project to be completed in 12 months. The budget of the project is 100,000 USD. Six months have passed, and 60,000 USD has been spent, but on closer review, you find that only 40% of the work has been completed so far.

What is the project’s Actual Cost (AC)?

The Actual Cost is the amount of money that you have spent so far.

In the question, you have spent 60,000 USD on the project so far.

Hence,

The project’s Actual Cost is 60,000 USD.

Applications of AC

AC drives financial health checks:

  • Compute cost variance (CV = EV – AC).
  • Build cost performance index (CPI = EV / AC; aim for >1.0).
  • Adjust forecasts in tools like Microsoft Project.

Pro Tip: Automate AC tracking with cloud software to catch variances weekly.

Earned Value (EV): Measuring True Progress

Earned Value is the budgeted Cost of work actually completed. It answers: “What has this spending produced?” If the project ended today, EV shows the value of your deliverables.

The PMBOK Guide 7th edition defines the EV as “The measure of work performed expressed in terms of the budget authorized for that work.”

PV plans the Value; EV delivers it. This distinction is key for stakeholders demanding ROI proof.

Although all three elements are significant, Earned Value is more useful because it shows how much Value you have earned from the money you have spent to date.

Earned Value is also known as the Budgeted Cost of Work Performed (BCWP).

There is a difference between Planned Value and Earned Value. Planned Value shows you how much Value you have planned to earn in a given time, while Earned Value shows you how much Value you have actually earned on the project.

Formula for Earned Value (EV)

The formula to calculate Earned Value is also simple. Take the actual percentage of completed work and multiply it by the project budget to get the Earned Value.

EV = (Actual % Complete) × BAC

Example of Earned Value (EV)

You have a project to be completed in 12 months. The budget of the project is 100,000 USD. Six months have passed, and 60,000 USD has been spent. On closer review, you find that only 40% of the work has been completed so far.

What is the project’s Earned Value (EV)?

In the above question, you can clearly see that only 40% of the work is actually completed, and the definition of Earned Value states that it is the Value of the project that has been earned.

Earned Value = 40% of the Value of the total work

= 40% of BAC

= 40% of 100,000

= 0.4 X 100,000

= 40,000 USD

Therefore, the project’s Earned Value (EV) is 40,000 USD.

Applications of EV

EV powers advanced forecasting:

  • Schedule variance and SPI for timelines.
  • Cost variance, CPI, estimate at completion (EAC), and to-complete performance index (TCPI).
  • Agile adaptations, like story point valuation.

In practice, EV boosts transparency: Teams see progress beyond Gantt charts.

In your PMP exam, you will be given a scenario and asked to identify these three elements. Please note that these elements are also known by different names, such as Planned Value (Budgeted Cost of Work Scheduled, BCWS), Actual Cost (Actual Cost of Work Performed, ACWP), and Earned Value (Budgeted Cost of Work Performed, BCWP).

It is unlikely that you will see these terms in your PMP exam, so concentrate on the terms mentioned in the PMBOK Guide rather than these outdated names.

Comparing PV, EV, and AC

It’s easy to confuse these three metrics because they all measure dollars. The table below summarizes their differences:

MetricWhat it RepresentsFormula/Calculation
Planned Value (PV)Authorized budget for work scheduled to be completed by a specific date% of work scheduled × BAC
Actual Cost (AC)Total money spent to dateSum of costs incurred
Earned Value (EV)Budgeted Value of work actually completedActual % complete × BAC

PV is about what you planned to accomplish, EV measures what you have accomplished, and AC reflects what you spent. Understanding these differences is the foundation of EVM.

Planned Value, Earned Value, and Actual Cost Chart

The chart shows how Planned Value, Earned Value, and Actual Cost change over time. PV rises steadily as work is planned. EV shows real progress, climbing faster early on. AC increases more slowly, suggesting efficiency. After 10 weeks, EV flattens, signaling project completion or halted progress.

image showing pv, ev, and ac chart

Derived Metrics: From Variances to Indexes

The power of EVM comes from the metrics you derive from PV, EV, and AC. 

The following are the derived metrics you can use to understand the project status and progress:

  • Schedule Variance (SV) = EV – PV. A positive SV means you are ahead of schedule; a negative SV means you are behind.
  • Cost Variance (CV) = EV – AC. A positive CV shows you are under budget; a negative CV shows you are over budget.
  • Schedule Performance Index (SPI) = EV ÷ PV. SPI indicates schedule efficiency. An SPI of 1 means you are on schedule.
  • Cost Performance Index (CPI) = EV ÷ AC. CPI measures cost efficiency. A CPI greater than 1 means you are spending less than planned.
  • Estimate at Completion (EAC) = BAC ÷ CPI. This formula predicts your project’s final Cost if current trends continue.
  • Estimate to Complete (ETC) = EAC – AC. ETC tells you how much more you need to spend to finish the project.
  • Variance at Completion (VAC) = BAC – EAC. A positive VAC means you expect to finish under budget.

Knowing these numbers lets you take corrective action. For example, if your SPI is 0.8 and your CPI is 0.67, you are both behind schedule and overspending. You would need to focus on cost control and investigate why the work is slower and more expensive than planned.

Key Formulas and Variance Calculations

With PV, EV, and AC in hand, you can calculate variances and indexes quickly. 

Here’s a quick reference:

MetricFormulaInterpretation
Schedule Variance (SV)EV – PVPositive: Ahead; Negative: Behind
Cost Variance (CV)EV – ACPositive: Under budget; Negative: Over
Schedule Performance Index (SPI)EV / PV>1: Efficient; <1: Delayed
Cost Performance Index (CPI)EV / AC>1: Cost-effective; <1: Overrun risk

Expanded Example: In our scenario (PV=$50,000, EV=$40,000, AC=$60,000), calculate variances and indexes:

  • SV = $40,000 – $50,000 = -$10,000 (behind schedule)
  • CV = $40,000 – $60,000 = -$20,000 (over budget)
  • SPI = 0.80 (20% behind)
  • CPI = 0.67 (33% over Cost)
  • Schedule Variance (SV): The difference between planned progress and actual progress.
  • Cost Variance (CV): The difference between the value of work completed and the actual cost incurred.
  • Schedule Performance Index (SPI): A ratio that shows how efficiently time is being used in a project.
  • Cost Performance Index (CPI): A ratio that measures how efficiently the project is using its budget.

Now, you can analyze your progress and take corrective and preventive actions to bring the project on track.

Real-World Applications and 2025-26 Trends

EVM isn’t theoretical—it’s battle-tested. In construction, it cuts overruns by 20-30% through weekly reviews. For software teams, adapt EV to agile by weighting user stories.

2025 Trends: Cloud-based EVM tools are booming, with the market expected to reach $1.5 billion by 2033, per industry forecasts. Predictive EVM uses AI to forecast risks, reducing overruns by 27% in large projects. In the PMBOK 7th edition, EVM aligns with the performance domains to provide holistic views.

Case Study: A 2024 telecom rollout used EV to recover from a 15% delay, saving $2M via CPI adjustments. Apply this: Run monthly EVM audits.

FAQs

Q1. What is the main difference between PV, EV, and AC?

Planned Value represents how much budgeted work should be completed; Earned Value measures how much budgeted work has been completed; Actual Cost shows how much money you’ve actually spent.

Q2. How often should I calculate EV and AC?

It’s a good practice to update these metrics at regular intervals, such as weekly or monthly, to detect trends and take corrective actions early.

Q3. Can I use EVM for agile projects?

Traditional EVM suits projects with linear schedules. For agile projects, adapt EVM by aligning PV with planned story points and EV with completed stories. Keep iterations short.

Q4. What if my CPI is below 1?

A CPI below 1 means you are spending more than the Value of work delivered. Review resource usage, find cost drivers, and take corrective action.

Q5. Is EVM required for PMP certification?

Yes. EVM is a core topic for the PMP® exam. Understanding PV, EV, and AC will help you answer questions on Cost and schedule performance.

Summary

Understanding Planned Value, Earned Value, and Actual Cost gives you a powerful insight into your project’s performance. PV shows what you planned to achieve, EV tells you what you have actually achieved, and AC reveals what you spent. By combining these metrics, you can calculate variances and performance indexes that offer early warnings and guide decisions.

EVM helps you identify schedule and cost variances early, reduce risks, and improve decision?making. Whether you are preparing for the PMP® exam or managing a real project, mastering these concepts will help you deliver on time and on budget.

Further Reading:

This concept is important from a PMP exam point of view.

Fahad Usmani, PMP

I am Mohammad Fahad Usmani, B.E. PMP, PMI-RMP. I have been blogging on project management topics since 2011. To date, thousands of professionals have passed the PMP exam using my resources.

PMP Question Bank

This is the most popular Question Bank for the PMP Exam. To date, it has helped over 10,000 PMP aspirants prepare for the exam. 

PMP Training Program

This is a PMI-approved 35 contact hours training program and it is based on the latest exam content outline applicable in 2026.

Similar Posts

89 Comments

  1. I want to say thank you for your extraordinary notes. Please help me understand the difference between Rules of Credit and Performance measurement. And how can I establish rules of credit for a project.

    Will

  2. Apart from the calculations, I am wondering if there are the factors that can cause a discrepancy between actual costs (AC) and planned value (PV).

  3. A general comment about the CV and CPI definitions. Both of them relate EV and AC performance variables. But the Earned Value (EV) has nothing to do with the execution cost (AC). Then, why when you define the BAC at the beginning of a project you don´t have a Cost Estimate variable similar to the PV, in order to compare the Actual Cost with the Planned Cost?
    Thanks in advance

  4. I have one question, in the graphic, EV, PV, and AC chart, you have that the EV curve falls down to zero after period #10, which is probably a mistake because you can´t lose the earned value you have gotten before that period. Suppose you don’t add value between periods 10 and 12, then the curve should keep the value reached before, which should be shown as a horizontal line at the value reached at period #10.

    1. hie, i think think the graph is correct, here we are not looking at cumulative earned value, but value earned for each month.

  5. – Project’s total budget is 1,5m€
    – 50 milestones, which have a same amount of financial resources and same length in time
    – Development time for entire project is 4 years

    The situation is following after the first year
    – You have spent the money in this stage 315 000€
    – You have performed 9 milestones

    Calculate the key figures using EVM technique.

    1. 2 / 2

      To calculate the key figures using the Earned Value Management (EVM) technique, we need to determine the Planned Value (PV), Earned Value (EV), and Actual Cost (AC) for the project.

      Given information:

      Total budget (B) = 1,500,000€
      Number of milestones (N) = 50
      Development time for the entire project = 4 years

      After the first year:

      Money spent (AC) = 315,000€
      Number of milestones completed (n) = 9

      Calculations:

      Planned Value (PV): This represents the planned cost of the work scheduled to be completed.
      PV = (n / N) * B
      PV = (9 / 50) * 1,500,000€
      PV = 270,000€

      Earned Value (EV): This represents the value of the work actually performed.
      EV = (n / N) * B
      EV = (9 / 50) * 1,500,000€
      EV = 270,000€

      Actual Cost (AC): This represents the actual cost incurred for the work completed.
      AC = 315,000€ (given)

      Now that we have the PV, EV, and AC, we can calculate the key EVM figures:

      Cost Variance (CV): This measures the difference between the earned value and the actual cost.
      CV = EV – AC
      CV = 270,000€ – 315,000€
      CV = -45,000€

      Schedule Variance (SV): This measures the difference between the earned value and the planned value.
      SV = EV – PV
      SV = 270,000€ – 270,000€
      SV = 0€

      Cost Performance Index (CPI): This indicates the cost efficiency of the project.
      CPI = EV / AC
      CPI = 270,000€ / 315,000€
      CPI ? 0.857

      Schedule Performance Index (SPI): This indicates the schedule efficiency of the project.
      SPI = EV / PV
      SPI = 270,000€ / 270,000€
      SPI = 1

      These are the key figures calculated using the EVM technique based on the given information after the first year of the project.
      Was this response better or worse?
      – Project’s total BAC 1.5m€
      – 50 milestones, which have a same amount of financial resources and same length in time
      – Development time for entire project is 4 years

      The situation is following after the first year
      – You have spent the money in this stage 315 000€
      – You have performed 9 milestones

      Calculate the key figures using EVM technique.
      Free Research Preview. ChatGPT may produce inaccurate information about people, places, or facts. ChatGPT May 24 Version

      1. I’m thinking your Planned Value is wrong since it did not take into consideration the number of years. The project is scheduled for 4 years and the snapshot is considered for 1year. 9 miles stones is an actual performance not a planned performance. However 1 year is a planned time period, this should give a better indication of the plan.

        Hence
        PV = 1/4 of 1.5m
        PV = 375,000

  6. Abigeal assigned a building project to your team, and you are asked to play the role of the project
    manager. The project is proposed to be completed in 8months after allocation, considering the internal
    and external factors. The estimated budget for the building project is 8Million but as at the 6th month,
    Abigeal realized that your team has executed only 40% of the proposed project and 4Million expended
    already.
    As a project manager, please undertake a project financial budget breakdown to ascertain if the project
    will be achievable within budget and time frame considering the following;
    1. PV
    2. EV
    3. AC
    4. CV
    5. SV
    6. CPI and
    7. SPI
    this question is confusing, i need help pls

    1. BAC = 8m
      AC = 4m
      Total time = 8 months
      Time spent = 6 months
      Performance = 40%
      PV = 6/8 of 8m = 6m
      EV = 40% of 8m = 3.2m
      CV = EV – AC = 0.8m
      SV = EV – PV = -2.8m
      CPI = EV/AC = 0.8
      SPI = EV/AC = 0.53

      The project is behind schedule and over budget.

  7. Hi Fahad Usmani,
    I’d appreciate if you can calculate for me please:

    A concrete slab project has a budget of $25,000 and after 40% of the concrete pour, remaining price increased to $85,000 due to price escalation. What is cost Variance and schedule variance.

    Thanks,
    Ramesh

  8. Your project is 50% of the way through its planned duration. It has spent 40% of the amount that was budgeted for the total project, and has completed 50% of the total work

    I’m not too sure which value I am able to use to calculate this cost. Can anyone help me?

  9. Hi, I can’t find examples for where the project has already over-run the planned end date.
    * Planned duration: 100 days
    * Current duration: 200 days
    * BAC = 100,000

    Does this mean my PV$ = $200,000 and PV% = 200% ???????

    This seems strange because the actual budget was only 100k, so surely I can’t “plan” to spend more than that much? But then again, this value gives me an SPI that calculates a useful completion date.

    In a report, should I show PV$ as $100k or $200k?

    1. Paul,

      Your PV will never be greater than your BAC, so at day 100 your PV becomes $100k and stays there. Unfortunately, once PV=BAC, SPI becomes less useful (as it approaches 1 with increased EV). Using Current Duration / EV% would give a meaningful forecast Finish Duration.

  10. The BAC of a small project is $100,000. So far $40,000 has been spent to deliver work worth $30,000. What will be the cost estimate to finish the project, assuming future work will be done at the budgeted rate?

    1. ETC = (BAC-EV)/CPI
      CPI = EV/AC
      CPI = 30,000/40,000
      CPI =0.75
      ETC = (100,000-40,000)/0.75
      ETC = $80,000
      Therefore, the cost estimate to complete the work will be $80,000.

  11. Hi Fahad,
    Could you tell me about the project cost mean. Are the project cost including staff salary, operation, insurance etc? and how to measure EV and PV of that item? Thanks.

    1. Yes, they are included and EV and PV are measured against cost baseline and actual baseline. You do not measure PV or EV for salary, operation, or insurance, etc.

  12. Hi fahad,pls can a project manager assume d progress of a project as 90% because it was done in 90 hours out of the planned 100hrs.
    Thanks

  13. One question
    project duration is 12 month.
    but project have delay after 12 month, how i can calculate PV?
    Thanks

  14. Hi!! What is the difference between Variance Formulas EV-xx (AC or PV)
    and what is the relation between Index Formulas EV/xx (AC or PV)
    THANKS

  15. In order to find Future Value which formula is correct to calculate from PMP point of view

    1. FV=PV(1+r)n where n is the power of (1+r) and PV is Present value, r is rate of interest & n is time period i.e number of years

    2. FV=PV(1+r/100)n where n is the power of (1+r/100)

    3. FV=CF [1-1/(1+r)n]/r + CF[1/(1+r)n] where n is the power of (1+r) , CF is the cash flow

  16. Need your help in understanding the planned value (PV) with the example :
    a. Project started in Oct 2014;
    b. Project will be completed in 28 months from Oct 2014;
    c. Below was the month on month Budget value, Earned Value and Actual cost;
    Particulars Oct 2014 Nov 2014 Dec 2014 Jan 2015 Feb 2015 Mar 2015 April 2015 Total
    Budget (BAC) 3450 3000 3200 3000 3500 3400 3500 26550
    Earned Value (EV) 3450 2800 3000 2800 3200 3200 3400 21850
    Actual Cost (AC) 3450 0 3000 2500 3000 2000 1000 14950

    With your above practical example in this article, it seems that PV = EV for the period already passed.

    Please advice.

    Thanks & Regards,
    Hemang Shah

    1. BAC = 23050(upto Apr’15) + 26550 = 49600

      Duration complete is 7 months out of 28 months = 25%

      PV = 25% of BAC
      i.e., PV = (25/100) * 49600
      therefore, PV = 12400
      EV = 21850
      AC = 14950

      is this correct..???

  17. hi all, i’m new to this post and i found the conversation and calcualtion was very detail and simple. im doing my pmp prep and i want someone to help me out on the below actual project scenario to find out PV and EV.,

    project duration – 4months authority approval + 8 months construction = 12months total
    project total cost = 13,500,000 (BAC)
    at the end of 75th day, i’ve obtained 5 authority approvals out of 7 and ongoing.
    i paid so far = 12,000 (AC)
    advance payment = 20 % of BAC, not paid.

    i got confused while calcualting the PV and EV, as i’ve only so much details as per the current project situation.

    help me out in find out the PV, EV

    Bala

  18. Can you please tell me how we can work out in this question ??
    An activity on the critical path of a project was scheduled to be completed within 16 weeks, with a budget of £8000. During a performance review, which took place 8 weeks after the activity was initiated, it was found that 60% of the work had already been completed and that the actual cost was £6000.
    (a) Calculate the Earned Value (EV) of the activity.
    (b) Calculate the Cost Performance Index (CPI) and the Schedule
    Performance Index (SPI) for the activity.
    (c) Based on the performance so far, provide an estimate for the expected budget at completion.
    (d) The management argues that the expected budget at completion could stay at £8000. Discuss the assumptions behind this argument.

    1. Budget at Completion (BAC) is £8,000

      Earned Value (EV) = 60% of 8,000 = £4,800

      Actual Cost (AC) = £6,000

      Planned Value (PV) = 50% of £8,000 = £4,000 (Since 50% of time has passed, so let us assume that 50% of work should be completed).

      I hope now you can calculate the rest of things…

  19. How do I calculate the PV, EV and AC for an activity tha finished 2 weeks behind schedule with a cost of $100,000. It was to have a cost of $110,000.

    1. Your AC is $100,000 because this is what you have spent.

      And EV is $110,000, because this is what you should have spent.

      And $110,000 is the PV, because this is what you have planned to spend. (corrected)

    2. Well, the main issue is when are you doing the calculation.

      If the calculation is done at the completion of the project.
      Then EV = PV = BAC

      however if the calculation is done at the orignal end date,
      then PV = BAC > EV.

  20. Dear Sir,

    Could you please explain the ways to get the ‘planned percent complete’ and ‘percent of work completed’.

    Thanks and Regards,
    Manish

    1. Usually these information are given in the question itself. Otherwise you can get it with either variance formulas or the performance index formulas.

  21. I still don’t understand the difference between PV and EV. Isn’t EV the same as AC – i.e. the actual amount of work that has been done? The definition of EV is very vague in the PMBOK as well as everywhere on the internet.

    1. Difference between these terms is very clear.

      Earned Value is the value of the completed work. Let us say that by this time you have completed 10% of the project and total worth of the project is 100,000 USD. In this case the Earned Value will be 10,000 USD.

      However, you notice that, to complete this much of work you have spend 15,000 USD. This is your Actual Cost.

      Again when you see your schedule, which says that by time you should have completed 13% of the work. This means that your Planned Value is 13,000 USD.

      Hope it helps.

  22. how can i get actual cost if i only have Assume that A project has planned value of $628,000 and earned value of $590,000 and that you have calculated a CV of negative $50,000. also what is ssume a typical variance

    Assume an atypical variance.

  23. Thank you for your very good explanation.

    Question: When we are talking about percentage of completion are we talking with regards to output, expenditure or time?

    For example, if my project is to make 100 cars in one year, but i buy all my materials upfront and this accounts for half my expenditure, then when is the project 50% complete? Is it:
    1) After ive made 50 cars
    2) After half a year
    3) After the first month when ive spent 50% of my planned budget

    Thank you.

    1. We are talking about the Values. For example, Earned Value, Actual Cost and Planned Value.

      Producing cars is an example of operation.

      Anyway I understand what you want to ask…

      You will always measure your performance against approved plan. If your plan says that you should have done these things to date, and you do not able to do so, you’re in bad shape.

      1. Thank you for your reply, im just trying to establish that where you have put ‘Percent complete – 50% (as per the schedule)’ how i can tell im 50% of the way through my project.
        Yes i agree if your plan is saying you should have completed more by a certain date then your behind schedule but that dosen’t tell you your percentage completion, just that your not where you planned to be.
        I’m sure it differs between projects but my question is whats the generic way of dividing up your project into 20%, 30%, 50%, before the project has begun…is it time related?

        Again thank you

  24. Need to answer this questions

    1. What is the actual cost to date? Is the project over or under budget?
    2. What is the SV for the project? Is the project ahead of or behind schedule?
    3. Calculate CPI and SPI.
    4. Assume a typical variance and calculate ETC and EAC.
    5. Assume an atypical variance and calculate ETC and EAC.

    Assume that A project has earned value of planned value of $628,000 and earned value of $590,000 and that you have calculated a CV of ($50,000).

  25. Can you help me to understand how the “0.375” in the answer was calculated.

    You are a project manager who is in charge of an important project for your company. The project is 40% complete after 3 months and has cost $350,000. The budget for the project is $950,000 and is scheduled to last 8 months. How is the project performing?
    Reason
    The project is ahead of schedule and under budget

    CPI=EV/AC CPI=(950,00*40%)/350,000 CPI=380,000/350,000 CPI=1.09(under budget); SPI=EV/PV SPI=380,000/(950,00 x 0.375) SPI=380,000/36,250 SPI=1.07 (ahead of schedule

    1. Hello Peggy,

      Let us calculate the Planned Value from the given question:

      Question says that the total budget is 950,000 USD, and the duration is 8 months.

      It means, you have to spend 950,000 USD in 8 months,

      Therefore, money to be spend in one month = 950,000*1/8
      and, money spend in three months = (950,000*1/8)*3
      = 950,000*3/8
      =950,000*0.375
      =356,250 USD

      Hope this helps.

  26. Dear Fahad,

    Your Examples on PV, EV & AC and very clear.
    I was struggling to know whats the difference between EV & AV, now you made me clear..
    thank you very much for the detailed explanation.

    Sesha.

    1. This was the first article of series of few posts in cost management. I suggest you read all articles in this series to gain understanding of cost management concepts; e.g. SPI, CPI, EAC, ETC, TCPI, etc.

      Fahad

  27. Hello Fahad..

    Can we apply the PV and EV concepts on FP projects using Fixed Milestone Billing (FMB) ?
    If yes, then could you please let me know how this would need to be calculated?

    1. Earn Value concepts provide you status of project and Fixed Milestone billing is way of making payment.

      It is up to you that how you plan to make payment. You may make payment on monthly basis based on status report or based on some other parameters….

  28. Your project has a BAC of $400,000 and is expected to last one year. The project work is scheduled to be completed in equal amounts each month. Currently, the project is in month three, but is only 20% complete. You have spent $35,000 to completed the work. What is the PV for this project?

    1. Hello Imran, sorry for this late reply. I was thinking that I have already replied.

      Anyway, solution is as follow:

      As the question says, the project work is scheduled to be completed in equal amounts in each month. Therefore, Planned Value to be spent in any single month is 400,000/12 which is $33,333.00

      Now, you’re saying that the project is in third month.

      Therefore, the money spend till the end of third month will be three times the money spend in one month; i.e. 3*33,333.000 which will be $100,000 USD.

      Hope this helps.

      1. Sir can we:

        (100% / 12) x 3 = 25%

        PV = 25% of 400,000 => $100,000 USD

        Will it be a right apporach to follow in future???

          1. one year project
            pv=130000
            ev= 100000
            ac= 150000
            bac= 900000

            Q1. how long the project doing?
            Q2. use the CPI to calculate the EAC?
            Q3. use the SPi to estimate how long it will take to finish this project?

            could you help me to find answer?

  29. I m still confused that what is the major difference between earned value and actual cost. What i perceived from you article is that earned value is in terms of the work which was performed/achieved at any spontaneous time and it has no concern with the cost involved in it whereas in actual cost the major parameter is the cost. Do correct me if i am wrong

    1. Let’s say that you have $100 project. At certain point you notice that you have spend $50.

      Therefore this $50 is you Actual Cost (AC).

      Now, on closer review you notice that only 40% of the project is completed. Therefore, Earn Value (EV) will be the 40% of total work; i.e. $40.

      1. Thanks Fahad Sb… for a moment Saad got me confused as well… BUT saved my undersading going off tarck..

        Can we say!!! AC is the amount of MONEY you have spent on a project at any pointif time???? BUT “EV” is the % completed by spending that MONEY???

        cause it might be possible that you have spent $80 but the completed work is only 30%

        So 80 becomes teh AC and 30% becmes the EV

        Right Sir??

          1. in that case, Earned Value is of more significance, which helps you understand your Project’s performance at any point in time. Whereas Actual Cost only gives you the realistic data..

            in simpler terms, EV is how much i should have spent for this work, AC is how much i actually spent.
            Please correct me if iam wrong..!

            Thanks Bro Fahad

  30. An amount of 25,000$ was given to a small project team to produce an application for the duration of 12months. Rate of performance for the project is 20,000$. The budget at completion (BAC) is 120,000$. Please how do i find the cost variance (CV), earned value (EV) and actual cost (AC)?
    Thank you.

    1. Hello Adeola,

      This question has some contradictory statements. You’re saying that project team has been given a 25,000$ money to produce an application within 12 months. According to this statement, BAC is 25,000$.

      Now again in same question, you are saying that BAC is 120,000$. How is this possible?

      1. Yes it got me confusing. Its actually a question from an assignment given to me.

        The original question is “Amount of 25,000$ (PV) was given to a small project team to produce simple android mobile application for the duration of 12 months. Rate of performance for the project is 20,000$(RP). The budget at completion is 120,000$.”

        I omitted (PV) from the earlier message. Does it make any sense now?

        1. Sorry Mr. Adeola but it still don’t make sense to me.

          The $25,000 is BAC for the project team, because project team has to complete the product from this amount.

          Now again you are saying that BAC is $120,000. How is it possible?

          1. Fahad,

            I hope you do not mind but I wanted to get in touch with you and could not find a way to directly email you. You wrote a very helpful article on this site regarding the three estimating methods and I would like to know if you know of any resources that show actual examples with each method applied.

            I am trying to understand the difference between Parametric estimating and Bottom Up as both seem to provide the same output to me. Please help me to understand if there is any difference.

            I appreciate any help you can provide and thank you for reading my message.

  31. For a project, I have Planned Value :1725.02
    Actual Cost is: 1709.02

    Can we figure out Earned Value from this?

    The system yielded 1865.91 which is higer than both numbers. Is this possible?

    Thanks

    1. No, you can not figure out the earned value from the given data.

      Yes, it is possible to have earned value more than the actual cost and the planned value.

      Hope it helps.

      1. Dear Sir,

        Why cant we calsulate EV from the given information????
        I mean, is NOT really possible OR the question require more information…

        BAC’s planned completion is PV
        BACs actual completion is EV
        Money spent so far from BAC is AC…

        So, is there no banlance equation combining ALL four in it…

        Something like PV + EV + AC = BAC???

        1. Let us say that you have completed the project. Just think that in this case how much you have spend, how much you have earned, and what is your planned value.

          If we go by your formula

          BAC = PV + EV + AC

          BAC = 3 times of BAC (approximately)

          This is so because at the end of your project, planned value will be equal to BAC, and about equal amount has been spent to complete it same amount is earned.

          Therefore your formula is not correct.